Description
Karaha Geothermal Power Plant is a part of Indonesian Government plans through PGE to utilise its geothermal reserves to strengthen its power industry and reduce geothermal reserves. In spite of having nearly 30,000MW of potential geothermal source, only 5% of it is utilised by Indonesia to meet its power requirements. The project involves the installation of a 30MW geothermal plant awarded
Scope of Works
Freyssinet is responsible to install post-tensioned basin slab as part of water tightness and crack control of the basin and coldwell cooling tower.
Client PERTAMINA GEOTHERMAL ENERGY (PGE)
Main Contractor ALSTOM
Civil Works HAWKINS BCK JO
Designer BECA
Years of involvement 2016